Revetment Works at Al Marfa (North Side)
Al Marfa, Abu Dhabi, UAE
Client
SSPD Sheikh Suroor Projects Department
Contract Type
Main Contractor
Completion Date
July 8, 2024
Scope of Works
Installation of Backfill Materials and shape the area with a slope of 1.5
Supply and Install 1000 gsm Geotextile with an area of approximately 288 sqm.
Supply and install 317 Tons of Quarry Run as Underlayer
Supply and install 380 Tons of Primary Armour Rock
Project Photos
![](https://static.wixstatic.com/media/4139f4_b5bbd058d9284e82ad33b94ab592d979~mv2.jpeg/v1/fill/w_165,h_234,q_90/4139f4_b5bbd058d9284e82ad33b94ab592d979~mv2.jpeg)
![](https://static.wixstatic.com/media/4139f4_a944502b9efd4ac987c58e6c263b6a77~mv2.jpeg/v1/fill/w_331,h_234,q_90/4139f4_a944502b9efd4ac987c58e6c263b6a77~mv2.jpeg)
![](https://static.wixstatic.com/media/4139f4_23f33aef27604bc99a1df5f3f9700f7c~mv2.jpeg/v1/fill/w_331,h_234,q_90/4139f4_23f33aef27604bc99a1df5f3f9700f7c~mv2.jpeg)
![](https://static.wixstatic.com/media/4139f4_c4c3de49273442c5931ddbc66965bcff~mv2.jpeg/v1/fill/w_165,h_234,q_90/4139f4_c4c3de49273442c5931ddbc66965bcff~mv2.jpeg)
![](https://static.wixstatic.com/media/4139f4_7e0d200a8fc7442dbd34e309fdab211e~mv2.jpg/v1/fill/w_638,h_359,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/4139f4_7e0d200a8fc7442dbd34e309fdab211e~mv2.jpg)
bottom of page